Implementing the next phase of an energy audit

Feb. 20, 2014
This article explores the implementation and sustaining phases of an energy audit.

Once an energy audit team presents its findings, along with a prioritized list of actions, decision makers must decide which — if not all — recommendations should be implemented. (Keep in mind, unless the cost benefits of the recommendations are attractive, decision makers will focus on other compelling budget priorities.) Then, for those projects getting the go-ahead, the third phase of the energy audit cycle can begin.

Implementing phase: The first step in the third phase of the energy audit cycle (Phases 1 and 2 were highlighted in last month’s column) is to develop an implementation plan. Each team should include members from relevant disciplines. Some recommendations, such as fixing steam leaks and reducing excess air levels at the fuel-fired boilers and heaters are straightforward and require obvious actions. These projects can be started quickly, typically yield quick results, and require zero or little capital investment.

For instance, in a graphite plant that molds and bakes calcined petroleum coke powder into large-sized electrodes, an energy expert attempted to control excess air at one of several baking furnaces to record the best-achievable operational settings. Because the baking cycle undergoes several stages of heating over a 72-hr period, a portable flue gas analyzer, along with the recordings of the existing on-line flue-gas oxygen analyzer, monitored and adjusted hourly the excess air level. Due to its capability of measuring the CO and combustible gas contents in flue gas, the portable flue gas analyzer trimmed the oxygen levels. A fuel-oil flow totalizer also recorded hourly readings from the baking furnace. This oxygen-trimming exercise resulted in developing a chart of operational settings for the baking furnace that established just 5% excess air achieved complete combustion at some stages of the baking cycle. The exercise also reduced fuel oil consumption 12% compared to the average fuel oil use per cycle recorded earlier in that same furnace.

Read the whole story on Chemical Processing

Sponsored Recommendations

The Need for Speed: The Most Advanced Sealless Pump is Also the Fastest

Jan. 14, 2025
Struggling with a troublesome pump? Get a reliable solution in just five days with the fastest, most advanced sealless pump on the market.

Ready to Reduce the Cost of Energy with a Highly Efficient, More Forgiving Pump?

Jan. 14, 2025
INNOMAG® pumps save energy and maintain peak efficiency over time—no wear and tear. Discover how they can lower your operating costs and increase reliability.

Tired of That Stubborn Pump That Just Won't Stop Leaking?

Jan. 14, 2025
Say goodbye to leaks for good. Discover how the hermetically sealed INNOMAG® pump delivers leak-free performance—even under the toughest conditions.

Ready to Start Simplifying your Pump Fleet?

Jan. 14, 2025
Streamline your operations with INNOMAG® pumps. Featuring a single material with near-universal chemical resistance, they deliver reliable performance across a wide range of application...